EXPANSION OF GOLDEN GATE BLVD. NAPLES FL

Register with us in one easy step!
avatarUdut, Kenneth -- on June 15 2009, from Golden Gate Estates, Naples, FL
Founder of this Naples site of NeighborHelp Referrals.

To be completed in 2013, the design for the project is 90% completed as of June 13, 2009. Bike lanes, widening to four lanes and more!

GOLDEN GATE BOULEVARD (Wilson Boulevard to DeSoto Boulevard) –

Plans to widen Golden Gate Boulevard from two lanes to four lanes are at the 90% design phase.

The plans will include capacity improvements such as adding turn lanes to the Wilson Boulevard and Everglades Boulevard intersections.

Other improvements include traffic signal upgrades at three major intersections (Wilson, Everglades and DeSoto Boulevards), on-road bike lanes and sidewalks on both sides of the roadway.

The project will also include the replacement of bridges over three canals, the Golden Gate, Miller and Faka Union canals.

Construction on this approximately six-mile project is being planned in 2013 as funding availability permits. Updated 3-13-09